January 2018

Project Progress completed in January 2018:

  • Ground level fencing complete
  • Stormwater connected
  • Level 4-5 timber flooring completed
  • Level 4-6 joinery complete
  • Bike racks installed on lower basement

 

IMG 0810
IMG 1031
IMG 1041
IMG 1057

 

November 2017

Project Progress completed in November 2017:

  • Ground level landscaping completed
  • Level 3 joinery complete
  • Level 4 joinery installation commenced
  • Communal planter box constructed
  • "Fin"detail on level 8 complete

IMG 0477
IMG 0481
IMG 0483
IMG 0499

September 2017

Project Progress completed in September 2017:

  • Lift scaffolding removed 
  • Ballustrade panels installation progressed on 8th and 9th floor 
  • Shop window framing underway
  • Traffic light system for basement and ground levels installed
  • All flooring laid on ground and level 1
  • Kitchen appliances fitting off completed on Ground, level 1 and 2.

IMG 2673
IMG 2686
IMG 2687
IMG 2688
IMG 2690

October 2017

Project Progress completed in October 2017:

  • Lift installation completed
  • External cladding patched and sanded to level 9
  • Personnel hoist dismantled
  • Kitchen and wardrobe joinery on level 3 installed
  • Substation fitout commenced
  • "Fin"detail on level 8 and 9 balustrade began installation.

Fininstal
Substation
Substation1

August 2017

Project Progress completed in August 2017:

  • Bamboo timber flooring and carpet installation underway throughout levels 1 and 2
  • Stone bench tops installed in bathroom and kitchens
  • Kitchen appliances and splashbacks installation underway
  • Sectional tilt bar panel basement entry door installed
  • Elevator installation commenced 
  • Balustrade panels installation progressed to level 8