March 2018

Project Progress completed in March  2018:

  • Ground level foyer tiling complete
  • "Mayor Anderson" plaque installed
  • Line marking and basement seal underway
  • Foyer painting, Ground- 4 underway
  • Stone aggregate entrance landing complete

IMG 1755
IMG 1894
IMG 1936
IMG 2009

February 2018

Project Progress completed in February 2018:

  • Ground level fencing complete
  • Stormwater connected
  • Level 4-5 timber flooring completed
  • Level 4-6 joinery complete
  • Bike racks installed on lower basement

 

IMG 0810
IMG 1031
IMG 1041
IMG 1057

November 2017

Project Progress completed in November 2017:

  • Ground level landscaping completed
  • Level 3 joinery complete
  • Level 4 joinery installation commenced
  • Communal planter box constructed
  • "Fin"detail on level 8 complete

IMG 0477
IMG 0481
IMG 0483
IMG 0499

January 2018

Project Progress completed in January 2018:

  • Ground level fencing complete
  • Stormwater connected
  • Level 4-5 timber flooring completed
  • Level 4-6 joinery complete
  • Bike racks installed on lower basement

 

IMG 0810
IMG 1031
IMG 1041
IMG 1057

 

October 2017

Project Progress completed in October 2017:

  • Lift installation completed
  • External cladding patched and sanded to level 9
  • Personnel hoist dismantled
  • Kitchen and wardrobe joinery on level 3 installed
  • Substation fitout commenced
  • "Fin"detail on level 8 and 9 balustrade began installation.

Fininstal
Substation
Substation1