April 2018

Project Progress completed in April 2018:

  • Common areas landscaping complete
  • Contractors issuing final compliance certificates 
  • Handrails for all stairs have been installed
  • Letterboxes installed
  • Stage 1 final cleans have commenced

IMG 2164
IMG 2168
IMG 2212
IMG 2213
IMG 2214
IMG 2226

 

March 2018

Project Progress completed in March  2018:

  • Ground level foyer tiling complete
  • "Mayor Anderson" plaque installed
  • Line marking and basement seal underway
  • Foyer painting, Ground- 4 underway
  • Stone aggregate entrance landing complete

IMG 1755
IMG 1894
IMG 1936
IMG 2009

January 2018

Project Progress completed in January 2018:

  • Ground level fencing complete
  • Stormwater connected
  • Level 4-5 timber flooring completed
  • Level 4-6 joinery complete
  • Bike racks installed on lower basement

 

IMG 0810
IMG 1031
IMG 1041
IMG 1057

 

February 2018

Project Progress completed in February 2018:

  • Ground level fencing complete
  • Stormwater connected
  • Level 4-5 timber flooring completed
  • Level 4-6 joinery complete
  • Bike racks installed on lower basement

 

IMG 0810
IMG 1031
IMG 1041
IMG 1057

November 2017

Project Progress completed in November 2017:

  • Ground level landscaping completed
  • Level 3 joinery complete
  • Level 4 joinery installation commenced
  • Communal planter box constructed
  • "Fin"detail on level 8 complete