Project Progress completed in April 2017:

  • Car park blockwork commenced
  • Ground floor timber framing completed on all townhouses
  • First floor timber framing commenced

 

20170426 114709
20170426 114923
20170504 1253280

Project Progress completed in January 2017:

  • Ground slab for residences 1-7 has been poured and cured ready for the next stages of work to commence
  • All under slab services in place
  • Next stage is set out for carpark slab and ground level timber framing

20170426 114709
20170426 114923
20170504 1253280

Project Progress completed in November 2016:

  • Stormwater retention tank is starting to be laid and is scheduled for completion before the end of December.
  • Underground Stormwater and sewerage is in its final stage before the ground slab is poured.

 

IMG 8821

Project Progress completed in December 2016:

  • Trades departed the site for the festive season.
  • Trades set to return in January to continue works on ground level carpark.
  • From all of us at SP Projects we hope you have a merry Christmas and a happy and healthy New year.

Project Progress completed in October 2016:

  • Site Cut completed
  • Bored piers being marked out
  • Drilling Began
  • Slab to begin pouring early November
  • Storm water retention system excavation currently underway

 

 