January 2018
Project Progress completed in January 2018
- Timber decking installation on all residences completed
- Communal entry concrete path has been poured
- Splashbacks installed in all kitchens
- Powder room and bathroom mirrors installed
- Timber privacy screen fencing installed
- European Oak flooring installation commenced
- Above bonnet bicycle racks installed in garage
- Concrete Slab for outdoor storage sheds poured
- Tap wear installation commenced on all residences
- Privacy screen louvres installed
- Entry partitions framed and rendered
- Front yard fencing commenced
December 2017
Project Progress completed in December 2017
- Framing for decks commenced and completed
- Timber decking installation on all residences
- Communal entry path formwork commenced
- Stairwell hand rails installed
- Stone bench tops installed in all bathrooms and kitchens
- Walk in robe joinery installed
- External power points and lighting installed
- Shower screens installed in residences
- Ducted vents installed in kitchens and throughout
September 2017
Project Progress completed in September 2017
- External Cladding works complete on level 2
- Mechanical rough in completed
- Roofing works completed
- Internal plastering commencing
November 2017
Project Progress completed in November 2017
- Boundary fence removed and replaced
- Bathroom tiling commeced on all residences
- Basement garage ceiling plastering completed
- Basement garage electrical fitout commenced
- Under stair storage doors installed
- Kitchen joinery delivered on site and installation commenced
August 2017
Project Progress completed in August 2017
- External Cladding works begun on all dwellings on level 2
- Scaffolding installed.
- Electrical rough in underway and plumbing rough in completed
- Insulation sheeting installed internally
- Gas meters installed